Port Phillip planning changes
Every gazetted zoning and overlay change in Port Phillip since 12 Oct 2017.
Every gazetted zoning and overlay change in Port Phillip since 12 Oct 2017, grouped by suburb. Part of the statewide Victoria Rezoning Tracker.
24 of 35 changes matched to a single amendment, 7 ambiguous. See every amendment to this scheme →
Changes by suburb
St Kilda (7, latest 18 Oct 2018)
| Gazetted | Change | Suburb | Zone | Parcels | Area | Amendment |
|---|---|---|---|---|---|---|
| 18 Oct 2018 | Schedule change (same zone) | St Kilda | NRZ5 → NRZ7 | 1 | 1.9 ha | Amendment C122 |
| 18 Oct 2018 | Schedule change (same zone) | St Kilda | GRZ1 → GRZ10 | 1 | 1.5 ha | Amendment C122 |
| 18 Oct 2018 | Schedule change (same zone) | St Kilda | GRZ1 → GRZ12 | 1 | 1.7 ha | Amendment C122 |
| 18 Oct 2018 | Schedule change (same zone) | St Kilda | GRZ1 → GRZ11 | 4 | 7,502 m² | Amendment C122 |
| 18 Oct 2018 | Rezoned, similar housing capacity | St Kilda | C1Z → MUZ | 3 | 6.4 ha | Amendment C122 |
| 18 Oct 2018 | Schedule change (same zone) | St Kilda | GRZ1 → GRZ13 | 2 | 4,763 m² | Amendment C122 |
| 14 Dec 2017 | Schedule change (same zone) | St Kilda | GRZ3 → GRZ2 | 1 | 3.3 ha | Amendment C123 |
* dated by when the record took effect; no gazettal date within two weeks was found.
Port Melbourne (5, latest 9 Jul 2020)
| Gazetted | Change | Suburb | Zone | Parcels | Area | Amendment |
|---|---|---|---|---|---|---|
| 9 Jul 2020 | Allows more housing | Port Melbourne | GRZ1 → MUZ | 1 | 5,761 m² | Amendment C160port |
| 14 Dec 2017 | Allows less housing | Port Melbourne | R1Z → NRZ3 | 2 | 43.6 ha | Amendment C123 |
| 14 Dec 2017 | Allows more housing | Port Melbourne, Balaclava, Elwood +5 more | R1Z → RGZ1 | 14 | 46.1 ha | Amendment C123 |
| 14 Dec 2017 | Allows less housing | Port Melbourne | C1Z → GRZ1 | 1 | 3,377 m² | Amendment C123 |
| 14 Dec 2017 | Allows less housing | Port Melbourne | R1Z → NRZ4 | 1 | 20.7 ha | Amendment C123 |
* dated by when the record took effect; no gazettal date within two weeks was found.
South Melbourne (3, latest 29 May 2025)
| Gazetted | Change | Suburb | Zone | Parcels | Area | Amendment |
|---|---|---|---|---|---|---|
| 29 May 2025 | Taken out of housing | South Melbourne | CCZ1 → PPRZ | 1 | 2,386 m² | Amendment C223port |
| 14 Dec 2017 | Allows less housing | South Melbourne, Albert Park, Port Melbourne | R1Z → NRZ2 | 8 | 48.4 ha | Amendment C123 |
| 12 Oct 2017 | Taken out of housing | South Melbourne | CCZ1 → PPRZ | 1 | 8,533 m² | Amendment C135 |
* dated by when the record took effect; no gazettal date within two weeks was found.
Elwood (2, latest 14 Dec 2017)
| Gazetted | Change | Suburb | Zone | Parcels | Area | Amendment |
|---|---|---|---|---|---|---|
| 14 Dec 2017 | Allows less housing | Elwood, St Kilda, St Kilda East | R1Z → NRZ6 | 19 | 49.3 ha | Amendment C123 |
| 14 Dec 2017 | Allows less housing | Elwood, Balaclava, Ripponlea +3 more | R1Z → NRZ5 | 28 | 168 ha | Amendment C123 |
* dated by when the record took effect; no gazettal date within two weeks was found.
Albert Park (1, latest 14 Dec 2017)
| Gazetted | Change | Suburb | Zone | Parcels | Area | Amendment |
|---|---|---|---|---|---|---|
| 14 Dec 2017 | Allows less housing | Albert Park, Balaclava, Elwood +4 more | R1Z → NRZ1 | 21 | 296 ha | Amendment C123 |
* dated by when the record took effect; no gazettal date within two weeks was found.
Overlay changes
| Gazetted | Change | Suburb | Zone | Parcels | Area | Amendment |
|---|---|---|---|---|---|---|
| 5 Jun 2025* | Melbourne | HO | 1 | – | See scheme amendments | |
| 5 Jun 2025 | Melbourne, St Kilda | HO | 2 | – | Amendment C226port | |
| 1 Aug 2024 | St Kilda | HO | 1 | – | Amendment C199port | |
| 24 Dec 2021 | New heritage control | Melbourne, Elwood, St Kilda | HO | 5 | – | 2 amendments gazetted that day |
| 24 Dec 2021 | Albert Park, Balaclava | HO | 3 | – | 2 amendments gazetted that day | |
| 23 Apr 2021 | New heritage control | South Melbourne | HO | 1 | – | 2 amendments gazetted that day |
| 23 Apr 2021 | South Melbourne | HO | 1 | – | 2 amendments gazetted that day | |
| 30 Jul 2020 | New heritage control | St Kilda East, St Kilda | HO | 4 | – | Amendment C142port |
| 30 Jul 2020 | St Kilda East | HO | 2 | – | Amendment C142port | |
| 9 Jul 2020 | New heritage control | St Kilda | HO | 1 | – | Amendment C160port |
| 9 Jul 2020* | St Kilda, Melbourne | HO | 5 | – | See scheme amendments | |
| 15 Aug 2019* | Port Melbourne | HO | 2 | – | See scheme amendments | |
| 18 Oct 2018 | New heritage control | St Kilda | HO | 6 | – | Amendment C122 |
| 22 May 2018* | Port Melbourne | HO | 1 | – | See scheme amendments | |
| 21 Dec 2017 | New heritage control | South Melbourne | HO | 1 | – | 2 amendments gazetted that day |
| 19 Oct 2017 | New heritage control | Melbourne | HO | 1 | – | 2 amendments gazetted that day |
| 19 Oct 2017 | Albert Park, St Kilda East | HO | 2 | – | 2 amendments gazetted that day |
* dated by when the record took effect; no gazettal date within two weeks was found.
Filter these changes
| Gazetted | Change | Suburb | Council | Zone | Parcels | Area |
|---|
The filter data did not load, so these filters are unavailable. The page still lists the changes we published; try reloading.
Method, dating and limits
Method. Delora's own method, not an official classification. Each zone family is ranked by how much housing it generally allows (rural 1, low-density 2, neighbourhood and township 3, general residential 4, residential growth and housing choice 5, mixed use and commercial 1 6, activity centre and precinct 7, urban growth 8). A change to a higher rank reads as allowing more housing, to a lower rank as allowing less. Moving land out of every ranked zone (for example into an industrial or public-use zone) counts as taken out of housing, and the reverse as opened to housing. Urban Growth land that receives its permanent zone once a precinct is built out is shown separately, not as a downzoning. A change of schedule within one zone (GRZ1 to GRZ2) can tighten or loosen the local rules, so it gets no verdict. Legacy recodes (R1Z to GRZ, RDZ to TRZ) and moves between road, rail and public-land zones are administrative and excluded from the counts.
How a change is dated. Where the service records a gazettal date for the new zone or overlay within two weeks of it taking effect, that gazettal date is shown. Otherwise the date the new record took effect is shown instead, and marked as such on the notice.
Amendment numbers. Matched to a notice when exactly one planning scheme amendment was gazetted for that council on that date; shown as ambiguous when several were, and never guessed. There is no amendment-number field in the source data itself.
- FZ/RAZ/RCZ/GWZ/GWAZ/RUZ/RLZ — Rural and green-wedge zones: at most one dwelling on a large lot, often needing a permit.
- LDRZ — Low Density Residential: houses on large lots (typically 0.4 ha or more) with limited subdivision.
- NRZ/TZ — Neighbourhood Residential and Township: detached housing with limited growth; the most restrictive urban residential zones.
- GRZ/R1Z/R2Z/R3Z — General Residential (and the pre-2014 Residential 1-3 codes it replaced): moderate growth such as townhouses and dual occupancies.
- RGZ/HCTZ — Residential Growth, and Housing Choice and Transport: zones designated for more housing, with apartments and greater height.
- MUZ/C1Z/B1Z/B2Z/B5Z/CDZ/PDZ/CCZ/DZ — Mixed use, Commercial 1 and the comprehensive or precinct zones: apartments above or beside other uses, usually in centres.
- ACZ/PRZ — Activity Centre and Precinct: the highest-density urban zones, applied to major centres and precincts planned for intensive change.
- UGZ/UFZ — Urban Growth: greenfield land being turned into whole new suburbs under a precinct structure plan.
Honest limits.
- Zone-polygon history runs from 30 Jul 2017 onwards; earlier changes are gazettal records only, without a mapped boundary.
- Overlay history covers heritage, floodway, land subject to inundation, special building and bushfire management only — not every overlay type in the planning scheme.
- This shows the zone or overlay that applies. It does not say what a planning permit will allow — that depends on the zone schedule, any overlay and the specific proposal.
- The up/down classification is Delora’s own method, not an official one.