Every gazetted zoning and overlay change in Port Phillip since 12 Oct 2017.

2changes allowing more housing
9changes allowing less housing
17overlay changes
5 Jun 2025most recent gazetted change

Every gazetted zoning and overlay change in Port Phillip since 12 Oct 2017, grouped by suburb. Part of the statewide Victoria Rezoning Tracker.

Schedule change (same zone), 18 Oct 2018Schedule change (same zone), 18 Oct 2018Schedule change (same zone), 18 Oct 2018Schedule change (same zone), 18 Oct 2018Rezoned, similar housing capacity, 18 Oct 2018Schedule change (same zone), 18 Oct 2018Schedule change (same zone), 14 Dec 2017Allows more housing, 9 Jul 2020Allows less housing, 14 Dec 2017Allows more housing, 14 Dec 2017Allows less housing, 14 Dec 2017Allows less housing, 14 Dec 2017Taken out of housing, 29 May 2025Allows less housing, 14 Dec 2017Taken out of housing, 12 Oct 2017Allows less housing, 14 Dec 2017Allows less housing, 14 Dec 2017Allows less housing, 14 Dec 2017
More housingLess housingSchedule changeOther zone change

24 of 35 changes matched to a single amendment, 7 ambiguous. See every amendment to this scheme →

Changes by suburb

St Kilda (7, latest 18 Oct 2018)

St Kilda suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
18 Oct 2018Schedule change (same zone)St KildaNRZ5 → NRZ711.9 haAmendment C122
18 Oct 2018Schedule change (same zone)St KildaGRZ1 → GRZ1011.5 haAmendment C122
18 Oct 2018Schedule change (same zone)St KildaGRZ1 → GRZ1211.7 haAmendment C122
18 Oct 2018Schedule change (same zone)St KildaGRZ1 → GRZ1147,502 m²Amendment C122
18 Oct 2018Rezoned, similar housing capacitySt KildaC1Z → MUZ36.4 haAmendment C122
18 Oct 2018Schedule change (same zone)St KildaGRZ1 → GRZ1324,763 m²Amendment C122
14 Dec 2017Schedule change (same zone)St KildaGRZ3 → GRZ213.3 haAmendment C123

* dated by when the record took effect; no gazettal date within two weeks was found.

Port Melbourne (5, latest 9 Jul 2020)

Port Melbourne suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
9 Jul 2020Allows more housingPort MelbourneGRZ1 → MUZ15,761 m²Amendment C160port
14 Dec 2017Allows less housingPort MelbourneR1Z → NRZ3243.6 haAmendment C123
14 Dec 2017Allows more housingPort Melbourne, Balaclava, Elwood +5 moreR1Z → RGZ11446.1 haAmendment C123
14 Dec 2017Allows less housingPort MelbourneC1Z → GRZ113,377 m²Amendment C123
14 Dec 2017Allows less housingPort MelbourneR1Z → NRZ4120.7 haAmendment C123

* dated by when the record took effect; no gazettal date within two weeks was found.

South Melbourne (3, latest 29 May 2025)

South Melbourne suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
29 May 2025Taken out of housingSouth MelbourneCCZ1 → PPRZ12,386 m²Amendment C223port
14 Dec 2017Allows less housingSouth Melbourne, Albert Park, Port MelbourneR1Z → NRZ2848.4 haAmendment C123
12 Oct 2017Taken out of housingSouth MelbourneCCZ1 → PPRZ18,533 m²Amendment C135

* dated by when the record took effect; no gazettal date within two weeks was found.

Elwood (2, latest 14 Dec 2017)

Elwood suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
14 Dec 2017Allows less housingElwood, St Kilda, St Kilda EastR1Z → NRZ61949.3 haAmendment C123
14 Dec 2017Allows less housingElwood, Balaclava, Ripponlea +3 moreR1Z → NRZ528168 haAmendment C123

* dated by when the record took effect; no gazettal date within two weeks was found.

Albert Park (1, latest 14 Dec 2017)

Albert Park suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
14 Dec 2017Allows less housingAlbert Park, Balaclava, Elwood +4 moreR1Z → NRZ121296 haAmendment C123

* dated by when the record took effect; no gazettal date within two weeks was found.

Overlay changes

GazettedChangeSuburbZoneParcelsAreaAmendment
5 Jun 2025*Heritage control removedMelbourneHO1–See scheme amendments
5 Jun 2025Heritage schedule changedMelbourne, St KildaHO2–Amendment C226port
1 Aug 2024Heritage schedule changedSt KildaHO1–Amendment C199port
24 Dec 2021New heritage controlMelbourne, Elwood, St KildaHO5–2 amendments gazetted that day
24 Dec 2021Heritage schedule changedAlbert Park, BalaclavaHO3–2 amendments gazetted that day
23 Apr 2021New heritage controlSouth MelbourneHO1–2 amendments gazetted that day
23 Apr 2021Heritage schedule changedSouth MelbourneHO1–2 amendments gazetted that day
30 Jul 2020New heritage controlSt Kilda East, St KildaHO4–Amendment C142port
30 Jul 2020Heritage schedule changedSt Kilda EastHO2–Amendment C142port
9 Jul 2020New heritage controlSt KildaHO1–Amendment C160port
9 Jul 2020*Heritage control removedSt Kilda, MelbourneHO5–See scheme amendments
15 Aug 2019*Heritage control removedPort MelbourneHO2–See scheme amendments
18 Oct 2018New heritage controlSt KildaHO6–Amendment C122
22 May 2018*Heritage control removedPort MelbourneHO1–See scheme amendments
21 Dec 2017New heritage controlSouth MelbourneHO1–2 amendments gazetted that day
19 Oct 2017New heritage controlMelbourneHO1–2 amendments gazetted that day
19 Oct 2017Heritage schedule changedAlbert Park, St Kilda EastHO2–2 amendments gazetted that day

* dated by when the record took effect; no gazettal date within two weeks was found.

Filter these changes

Change type
GazettedChangeSuburbCouncilZoneParcelsArea

Method, dating and limits

Method. Delora's own method, not an official classification. Each zone family is ranked by how much housing it generally allows (rural 1, low-density 2, neighbourhood and township 3, general residential 4, residential growth and housing choice 5, mixed use and commercial 1 6, activity centre and precinct 7, urban growth 8). A change to a higher rank reads as allowing more housing, to a lower rank as allowing less. Moving land out of every ranked zone (for example into an industrial or public-use zone) counts as taken out of housing, and the reverse as opened to housing. Urban Growth land that receives its permanent zone once a precinct is built out is shown separately, not as a downzoning. A change of schedule within one zone (GRZ1 to GRZ2) can tighten or loosen the local rules, so it gets no verdict. Legacy recodes (R1Z to GRZ, RDZ to TRZ) and moves between road, rail and public-land zones are administrative and excluded from the counts.

How a change is dated. Where the service records a gazettal date for the new zone or overlay within two weeks of it taking effect, that gazettal date is shown. Otherwise the date the new record took effect is shown instead, and marked as such on the notice.

Amendment numbers. Matched to a notice when exactly one planning scheme amendment was gazetted for that council on that date; shown as ambiguous when several were, and never guessed. There is no amendment-number field in the source data itself.

  • FZ/RAZ/RCZ/GWZ/GWAZ/RUZ/RLZ — Rural and green-wedge zones: at most one dwelling on a large lot, often needing a permit.
  • LDRZ — Low Density Residential: houses on large lots (typically 0.4 ha or more) with limited subdivision.
  • NRZ/TZ — Neighbourhood Residential and Township: detached housing with limited growth; the most restrictive urban residential zones.
  • GRZ/R1Z/R2Z/R3Z — General Residential (and the pre-2014 Residential 1-3 codes it replaced): moderate growth such as townhouses and dual occupancies.
  • RGZ/HCTZ — Residential Growth, and Housing Choice and Transport: zones designated for more housing, with apartments and greater height.
  • MUZ/C1Z/B1Z/B2Z/B5Z/CDZ/PDZ/CCZ/DZ — Mixed use, Commercial 1 and the comprehensive or precinct zones: apartments above or beside other uses, usually in centres.
  • ACZ/PRZ — Activity Centre and Precinct: the highest-density urban zones, applied to major centres and precincts planned for intensive change.
  • UGZ/UFZ — Urban Growth: greenfield land being turned into whole new suburbs under a precinct structure plan.

Honest limits.

  • Zone-polygon history runs from 30 Jul 2017 onwards; earlier changes are gazettal records only, without a mapped boundary.
  • Overlay history covers heritage, floodway, land subject to inundation, special building and bushfire management only — not every overlay type in the planning scheme.
  • This shows the zone or overlay that applies. It does not say what a planning permit will allow — that depends on the zone schedule, any overlay and the specific proposal.
  • The up/down classification is Delora’s own method, not an official one.