Every gazetted zoning and overlay change in Moyne since 3 Oct 2017.

3changes allowing more housing
23changes allowing less housing
9overlay changes
17 Dec 2025most recent gazetted change

Every gazetted zoning and overlay change in Moyne since 3 Oct 2017, grouped by suburb. Part of the statewide Victoria Rezoning Tracker.

Allows less housing, 3 Oct 2024Allows more housing, 3 Oct 2024Taken out of housing, 3 Oct 2024Taken out of housing, 3 Oct 2024Taken out of housing, 3 Oct 2024Taken out of housing, 3 Oct 2024Schedule change (same zone), 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Schedule change (same zone), 3 Nov 2023Rezoned, similar housing capacity, 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Schedule change (same zone), 3 Nov 2023Taken out of housing, 3 Nov 2023Rezoned, similar housing capacity, 3 Nov 2023Schedule change (same zone), 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023Taken out of housing, 3 Nov 2023
More housingLess housingSchedule changeOther zone change

39 of 41 changes matched to a single amendment. See every amendment to this scheme →

Changes by suburb

Port Fairy (14, latest 3 Oct 2024)

Port Fairy suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Oct 2024Allows less housingPort FairyGRZ1 → NRZ17248 haAmendment C69moyn
3 Oct 2024Allows more housingPort FairyRLZ1 → NRZ1146.4 haAmendment C69moyn
3 Oct 2024Taken out of housingPort FairyGRZ1 → PUZ634,235 m²Amendment C69moyn
3 Oct 2024Opened to housingPort FairyPUZ3 → C1Z11,388 m²Amendment C69moyn
3 Oct 2024Taken out of housingPort FairyRLZ3 → PPRZ12.2 haAmendment C69moyn
3 Oct 2024Taken out of housingPort FairyFZ → PCRZ122.4 haAmendment C69moyn
3 Oct 2024Taken out of housingPort FairyFZ → PUZ11611 m²Amendment C69moyn
3 Oct 2024Taken out of housingPort FairyGRZ1 → PPRZ76,878 m²Amendment C69moyn
3 Oct 2024Taken out of housingPort FairyGRZ1 → PUZ12929 m²Amendment C69moyn
3 Oct 2024Taken out of housingPort FairyGRZ1 → PUZ31133 m²Amendment C69moyn
3 Oct 2024Opened to housingPort FairyPPRZ → NRZ111,710 m²Amendment C69moyn
3 Oct 2024Taken out of housingPort FairyGRZ1 → PCRZ14.6 haAmendment C69moyn
3 Oct 2024Taken out of housingPort FairyLDRZ → PCRZ22,474 m²Amendment C69moyn
3 Nov 2023Schedule change (same zone)Port Fairy, Mailors FlatRLZ → RLZ33712 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Unassigned land (3, latest 3 Nov 2023)
GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housing22861, PurnimFZ → PUZ124,538 m²Amendment C70moyn
3 Nov 2023Taken out of housing22861TZ → PCRZ16,075 m²Amendment C70moyn
3 Nov 2023Taken out of housing22861TZ → PUZ318,198 m²Amendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Caramut (2, latest 3 Nov 2023)

Caramut suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housingCaramut, 20944, Garvoc +6 moreTZ → PPRZ1518.8 haAmendment C70moyn
3 Nov 2023Taken out of housingCaramutTZ → PUZ112.5 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Hawkesdale (2, latest 3 Nov 2023)

Hawkesdale suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housingHawkesdale, Macarthur, WoolsthorpeTZ → PUZ642.1 haAmendment C70moyn
3 Nov 2023Taken out of housingHawkesdale, GrassmereFZ → PUZ227.4 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Illowa (2, latest 3 Nov 2023)

Illowa suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Schedule change (same zone)Illowa, 22197FZ → FZ221,546 haAmendment C70moyn
3 Nov 2023Rezoned, similar housing capacityIllowa, 22316FZ → RLZ24167 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Macarthur (2, latest 3 Nov 2023)

Macarthur suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housingMacarthur, WoolsthorpeTZ → PUZ223.8 haAmendment C70moyn
3 Nov 2023Taken out of housingMacarthur, 21418, 21949 +6 moreFZ → PPRZ1044.3 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Bushfield (1, latest 3 Nov 2023)

Bushfield suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Schedule change (same zone)BushfieldFZ → FZ31517 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Cudgee (1, latest 3 Nov 2023)

Cudgee suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housingCudgeeLDRZ → PUZ219,019 m²Amendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Grassmere (1, latest 3 Nov 2023)

Grassmere suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Rezoned, similar housing capacityGrassmere, 21348, Hawkesdale +1 moreFZ → RLZ15110 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Mortlake (1, latest 3 Nov 2023)

Mortlake suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Schedule change (same zone)Mortlake, Macarthur, Nullawarre +4 moreRLZ → RLZ1141,311 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Panmure (1, latest 3 Nov 2023)

Panmure suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housingPanmureRLZ → PUZ211.2 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Purnim (1, latest 3 Nov 2023)

Purnim suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housingPurnim, Panmure, WinslowRLZ → PPRZ311.0 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Woolsthorpe (1, latest 3 Nov 2023)

Woolsthorpe suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
3 Nov 2023Taken out of housingWoolsthorpe, Hawkesdale, PanmureFZ → PUZ5310.0 haAmendment C70moyn

* dated by when the record took effect; no gazettal date within two weeks was found.

Overlay changes

GazettedChangeSuburbZoneParcelsAreaAmendment
17 Dec 2025New bushfire controlWarrnamboolBMO1–Amendment GC267
3 Oct 2024New flood controlPort FairyLSIO1–Amendment C69moyn
3 Oct 2024Flood schedule changedPort FairyFO10–Amendment C69moyn
3 Oct 2024*Flood control removedPort FairyLSIO12–See scheme amendments
3 Oct 2024New flood controlPort FairyFO10–Amendment C69moyn
25 Feb 2021*Heritage control removed21696, Caramut, WoolsthorpeHO4–See scheme amendments
25 Feb 2021New heritage controlWoolsthorpe, 21696, CaramutHO8–Amendment C73moyn
3 Sep 2020New bushfire control22562, GrassmereBMO3–Amendment GC171
3 Oct 2017New bushfire control20225, 20325, 20347 +33 moreBMO104–Amendment GC13

* dated by when the record took effect; no gazettal date within two weeks was found.

Filter these changes

Change type
GazettedChangeSuburbCouncilZoneParcelsArea

Method, dating and limits

Method. Delora's own method, not an official classification. Each zone family is ranked by how much housing it generally allows (rural 1, low-density 2, neighbourhood and township 3, general residential 4, residential growth and housing choice 5, mixed use and commercial 1 6, activity centre and precinct 7, urban growth 8). A change to a higher rank reads as allowing more housing, to a lower rank as allowing less. Moving land out of every ranked zone (for example into an industrial or public-use zone) counts as taken out of housing, and the reverse as opened to housing. Urban Growth land that receives its permanent zone once a precinct is built out is shown separately, not as a downzoning. A change of schedule within one zone (GRZ1 to GRZ2) can tighten or loosen the local rules, so it gets no verdict. Legacy recodes (R1Z to GRZ, RDZ to TRZ) and moves between road, rail and public-land zones are administrative and excluded from the counts.

How a change is dated. Where the service records a gazettal date for the new zone or overlay within two weeks of it taking effect, that gazettal date is shown. Otherwise the date the new record took effect is shown instead, and marked as such on the notice.

Amendment numbers. Matched to a notice when exactly one planning scheme amendment was gazetted for that council on that date; shown as ambiguous when several were, and never guessed. There is no amendment-number field in the source data itself.

  • FZ/RAZ/RCZ/GWZ/GWAZ/RUZ/RLZ — Rural and green-wedge zones: at most one dwelling on a large lot, often needing a permit.
  • LDRZ — Low Density Residential: houses on large lots (typically 0.4 ha or more) with limited subdivision.
  • NRZ/TZ — Neighbourhood Residential and Township: detached housing with limited growth; the most restrictive urban residential zones.
  • GRZ/R1Z/R2Z/R3Z — General Residential (and the pre-2014 Residential 1-3 codes it replaced): moderate growth such as townhouses and dual occupancies.
  • RGZ/HCTZ — Residential Growth, and Housing Choice and Transport: zones designated for more housing, with apartments and greater height.
  • MUZ/C1Z/B1Z/B2Z/B5Z/CDZ/PDZ/CCZ/DZ — Mixed use, Commercial 1 and the comprehensive or precinct zones: apartments above or beside other uses, usually in centres.
  • ACZ/PRZ — Activity Centre and Precinct: the highest-density urban zones, applied to major centres and precincts planned for intensive change.
  • UGZ/UFZ — Urban Growth: greenfield land being turned into whole new suburbs under a precinct structure plan.

Honest limits.

  • Zone-polygon history runs from 30 Jul 2017 onwards; earlier changes are gazettal records only, without a mapped boundary.
  • Overlay history covers heritage, floodway, land subject to inundation, special building and bushfire management only — not every overlay type in the planning scheme.
  • This shows the zone or overlay that applies. It does not say what a planning permit will allow — that depends on the zone schedule, any overlay and the specific proposal.
  • The up/down classification is Delora’s own method, not an official one.