Every gazetted zoning and overlay change in Macedon Ranges since 15 Aug 2017.

4changes allowing more housing
5changes allowing less housing
11overlay changes
2 Apr 2026most recent gazetted change

Every gazetted zoning and overlay change in Macedon Ranges since 15 Aug 2017, grouped by suburb. Part of the statewide Victoria Rezoning Tracker.

Schedule change (same zone), 28 Aug 2025Allows less housing, 15 Aug 2017Allows less housing, 15 Aug 2017Allows more housing, 15 Aug 2017Change between non-housing zones, 15 Aug 2017Allows more housing, 19 Jun 2025Opened to housing, 20 Jun 2024Taken out of housing, 12 Aug 2021Schedule change (same zone), 12 Aug 2021Taken out of housing, 12 Aug 2021Allows more housing, 6 Jun 2024Taken out of housing, 12 Aug 2021
More housingLess housingSchedule changeOther zone change

16 of 23 changes matched to a single amendment. See every amendment to this scheme →

Changes by suburb

Riddells Creek (5, latest 28 Aug 2025)

Riddells Creek suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
28 Aug 2025Schedule change (same zone)Riddells CreekUGZ → UGZ11132 haAmendment C161macr
15 Aug 2017Allows less housingRiddells CreekGRZ1 → NRZ8175.2 haSee scheme amendments
15 Aug 2017Allows less housingRiddells CreekGRZ1 → NRZ7175.1 haSee scheme amendments
15 Aug 2017Allows more housingRiddells CreekRLZ1 → UGZ1132 haSee scheme amendments
15 Aug 2017Change between non-housing zonesRiddells CreekC2Z → SUZ513.5 haSee scheme amendments

* dated by when the record took effect; no gazettal date within two weeks was found.

Malmsbury (3, latest 19 Jun 2025)

Malmsbury suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
19 Jun 2025Allows more housingMalmsburyFZ → NRZ1313.1 haAmendment C154macr
20 Jun 2024Opened to housingMalmsburyC2Z → NRZ1411.6 haAmendment C157macr
12 Aug 2021Taken out of housingMalmsburyRLZ5 → PCRZ14.6 haAmendment C126macrPt1

* dated by when the record took effect; no gazettal date within two weeks was found.

Woodend (2, latest 12 Aug 2021)

Woodend suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
12 Aug 2021Schedule change (same zone)WoodendPUZ4 → PUZ717,436 m²Amendment C126macrPt1
12 Aug 2021Taken out of housingWoodendLDRZ → PCRZ16,196 m²Amendment C126macrPt1

* dated by when the record took effect; no gazettal date within two weeks was found.

Gisborne (1, latest 6 Jun 2024)

Gisborne suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
6 Jun 2024Allows more housingGisborneGRZ1 → C1Z14,888 m²Amendment C153macr

* dated by when the record took effect; no gazettal date within two weeks was found.

New Gisborne (1, latest 12 Aug 2021)

New Gisborne suburb page →

GazettedChangeSuburbZoneParcelsAreaAmendment
12 Aug 2021Taken out of housingNew GisborneRLZ2 → PCRZ110.3 haAmendment C126macrPt1

* dated by when the record took effect; no gazettal date within two weeks was found.

Overlay changes

GazettedChangeSuburbZoneParcelsAreaAmendment
2 Apr 2026New flood controlDarraweit GuimLSIO1–Amendment GC236
2 Apr 2026Flood schedule changedKyneton, 20172, 22078 +13 moreLSIO29–Amendment GC236
14 Sep 2023New heritage controlWoodend, Mount MacedonHO2–Amendment C159macr
14 Sep 2023*Heritage control removedKyneton, WoodendHO2–See scheme amendments
31 Aug 2023*Heritage control removedWoodendHO1–See scheme amendments
31 Aug 2023New heritage controlMount Macedon, 20541, Lancefield +3 moreHO34–Amendment C127macr
11 Jun 2020New heritage controlWoodendHO1–Amendment C132macr
20 Sep 2019*Heritage control removedNew GisborneHO1–See scheme amendments
24 Jan 2019New heritage controlMacedonHO1–Amendment C124macr
26 Apr 2018New heritage controlGisborne, 21415, Kyneton +1 moreHO40–Amendment C123
3 Oct 2017New bushfire controlBullengarook, 20172, 20435 +25 moreBMO70–Amendment GC13

* dated by when the record took effect; no gazettal date within two weeks was found.

Filter these changes

Change type
GazettedChangeSuburbCouncilZoneParcelsArea

Method, dating and limits

Method. Delora's own method, not an official classification. Each zone family is ranked by how much housing it generally allows (rural 1, low-density 2, neighbourhood and township 3, general residential 4, residential growth and housing choice 5, mixed use and commercial 1 6, activity centre and precinct 7, urban growth 8). A change to a higher rank reads as allowing more housing, to a lower rank as allowing less. Moving land out of every ranked zone (for example into an industrial or public-use zone) counts as taken out of housing, and the reverse as opened to housing. Urban Growth land that receives its permanent zone once a precinct is built out is shown separately, not as a downzoning. A change of schedule within one zone (GRZ1 to GRZ2) can tighten or loosen the local rules, so it gets no verdict. Legacy recodes (R1Z to GRZ, RDZ to TRZ) and moves between road, rail and public-land zones are administrative and excluded from the counts.

How a change is dated. Where the service records a gazettal date for the new zone or overlay within two weeks of it taking effect, that gazettal date is shown. Otherwise the date the new record took effect is shown instead, and marked as such on the notice.

Amendment numbers. Matched to a notice when exactly one planning scheme amendment was gazetted for that council on that date; shown as ambiguous when several were, and never guessed. There is no amendment-number field in the source data itself.

  • FZ/RAZ/RCZ/GWZ/GWAZ/RUZ/RLZ — Rural and green-wedge zones: at most one dwelling on a large lot, often needing a permit.
  • LDRZ — Low Density Residential: houses on large lots (typically 0.4 ha or more) with limited subdivision.
  • NRZ/TZ — Neighbourhood Residential and Township: detached housing with limited growth; the most restrictive urban residential zones.
  • GRZ/R1Z/R2Z/R3Z — General Residential (and the pre-2014 Residential 1-3 codes it replaced): moderate growth such as townhouses and dual occupancies.
  • RGZ/HCTZ — Residential Growth, and Housing Choice and Transport: zones designated for more housing, with apartments and greater height.
  • MUZ/C1Z/B1Z/B2Z/B5Z/CDZ/PDZ/CCZ/DZ — Mixed use, Commercial 1 and the comprehensive or precinct zones: apartments above or beside other uses, usually in centres.
  • ACZ/PRZ — Activity Centre and Precinct: the highest-density urban zones, applied to major centres and precincts planned for intensive change.
  • UGZ/UFZ — Urban Growth: greenfield land being turned into whole new suburbs under a precinct structure plan.

Honest limits.

  • Zone-polygon history runs from 30 Jul 2017 onwards; earlier changes are gazettal records only, without a mapped boundary.
  • Overlay history covers heritage, floodway, land subject to inundation, special building and bushfire management only — not every overlay type in the planning scheme.
  • This shows the zone or overlay that applies. It does not say what a planning permit will allow — that depends on the zone schedule, any overlay and the specific proposal.
  • The up/down classification is Delora’s own method, not an official one.